Project Scope

Biogas Products Ltd were contracted to supply and install 2no 1500m3 PVC membrane gas holders to replace existing gas holders on a Yorkshire Water site, Hull WwTW.

Working for main contractor JN Bentley, the installation was part of a £80m upgrade of the site.

Design Requirement

2no ¾ sphere PVC double membrane gas holders with a total capacity of 3000m3 working in parallel at a pressure of 18mbar.

Products and Services

The membrane gas holders are complete with common duty/standby air blowers, a common air pressure control valve which equalises the pressure in each gas holder, laser type gas holder level sensors, gas leak detection, viewing windows and an access door. All installed and commissioned by our own site installation team.

Outcome

The gas holders provide storage and a gas pressure in all operating conditions to maintain a sufficient supply to the CHP gas boosters.

Large rectangular membrane gas holder for Cambridge farm gas to grid project

Biogas Products Ltd have secured an order for a large rectangular membrane gas holder to be installed on a farm site in Cambridgeshire. Working with membrane technology provider Power Plastics, Biogas Products Ltd has developed a gas holder which is designed and...

Biogas Products Ltd – from biogas and wastewater to swimming pools and cruise liners

lBiogas Products Ltd have a large portfolio of technology primarily for the Biogas and Wastewater industry. However, over the years we have been asked to design and manufacture a range of equipment, incuding strainer baskets, that takes us beyond our usual realms of...

Biogas Products secure multiple gas holder installations in 2019

Biogas Products Ltd has secured an order to design, supply and install two membrane gas holders at Hull WwTW, for Yorkshire Water contractor JN Bentley. This comes shortly after being awarded a similar contract to install a new membrane gas holder at Oldham WwTW for...

Digester refurbishment works complete at Liverpool STW

Biogas Products Ltd have completed refurbishment works on a digester at Liverpool STW for Eric Wright, framework contractor to United Utilities. Work carried out on the anaerobic digester included the refurbishment of four mild steel upstands. These were removed from...

New gas holder and digester cover to be installed on Welsh farm

Biogas Products Ltd have just secured another order for a new 100m3 gas holder and insulated membrane digester cover on a farm site in South Wales. Adding to the already lengthy list of membrane gas holder installations in the UK, Biogas Products are one of the very...

Digester gets a facelift for the start of the new year

Biogas Products Ltd will be on-site at Liverpool STW on the run-up to Christmas. They will be repairing and refurbishing an anaerobic digester, for United Utilities framework contractor Eric Wright. The digester, which has been in operation for many years, is in need...

Biogas Products secure order for a new membrane gas holder at Oldham WwTW

Biogas Products Ltd are working with United Utilities contractor, Nomenca Ltd, to install a new 3000m3 gas holder at Oldham Wastewater Treatment Works, as part of an £80M upgrade of the site. Work on site is due to commence in the New Year and will take...

Welcome to our new website!

After 10 years in business, we thought it was time we refreshed our website and here it is! It was great working with Jayne at Evie Creative our new website, which offers more information, easier navigation and an all round better user experience. Plus we...