Recent Installations

Coca Cola
Coca Cola

Coca Cola Ltd Great Britain

Client - Coca Cola

Site - Coca Cola, Wakefield Plant

The existing membrane gas holder had reached the end of its working life. Biogas Products repaired the gas holder to provide further extended service while a replacement was procured. The original UPVc gas pipework system  was also found to be in poor condition. A new stainless steel system was designed, fabricated and installed..

Equipment supplied:-

1x 12m³ capacity 3 membrane gas holder
1x Stainless steel gas utilisation pipework system

Kerry Ingredients

Client - Edina Ltd

Site - Kerry Ingredients, Listowel, Ireland

The existing Anaerobic Digester installation cleaned and flared off the biogas produced. The plant has now been upgraded to provide biogas utilisation through CHP generation.

Equipment supplied:-

1x 540m³ capacity 3 membrane gas holder
4x Stainless steel condensate pots to suit 200mm gas pipework

Biogas Products Ltd ‘in-house’ design services developed drawings for the required 200m biogas pipeline which was installed by others.

Edina Ltd
Edina Ltd
Inbev UK
Inbev UK

Coca Cola Ltd Great Britain

Client - Inbev UK

Design Consultant - Lorien Enginineering Solutions

Site - Inbev Magor Brewery, Cardiff

The existing Anaerobic Digester installation cleaned and flared off the biogas produced. The plant has now been upgraded to provide biogas utilisation through CHP generation.

Equipment supplied:-

1x 200m³ capacity 3 membrane gas holder
1x Gas dehumidifier c/w condensate pot and automatic drain valve
1x Gas booster
1x hot water/biogas ‘in-line’ heat exchanger
1x Carbon filter (removal of residual H2S)
1x Siloxane filter

South West Water

Client - South West Water
Main Contractor - Interserve

Site - Nanstallon WwTW, nr Bodmin

The existing steel floating gas dome had reached the end of its working life. Due to space restrictions on site it was decided to remove the dome from the top of the digester, construct a flat concrete roof and install a ‘stand alone’ gas holder on top of the new concrete roof.

Equipment supplied:-

1x 100m³ 3 membrane gas holder
1x 4 post lightning protection system

South West Water
South West Water